SPEC SHEET

Atlas DC1 — Canonical Specifications

v1.0 · single source of truth · cited by all 32 sections

When a Power Atlas section quotes a number for Atlas DC1, that number comes from this page. If you find a contradiction between this page and a section, this page wins.

AI/HPC Density Note — Atlas DC1 spec assumes traditional rack density
Atlas DC1 is spec'd at ~ 12 kW per rack (104 racks per row × 12 kW = 1.25 MW per row). This is appropriate for traditional enterprise + cloud workloads. Modern AI/GPU workloads (training NVIDIA H100/H200 clusters, custom AI accelerators) push rack densities to 30-100+ kW per rack. At those densities, Atlas DC1's air-cooled architecture is inadequate. AI deployments require:
  • Liquid cooling (rear-door heat exchangers minimum, direct liquid cooling preferred) — see §35 Liquid Cooling
  • Rack-level power 30-100+ kW (vs Atlas DC1's ~ 12 kW) — requires busway down each row instead of branch circuits
  • Sub-millisecond network fabric (NVLink, InfiniBand) — fundamentally different cabling architecture
  • Power density 300-1000+ kW per row (vs Atlas DC1's 1.25 MW per row)
Atlas DC1 is intentionally a representative TRADITIONAL DC. For AI/HPC, see §36 AI/HPC Data Center Design.

Facility Profile

ParameterValueSource / rationale
TypeMulti-tenant colocation data centerReference scale — small enough to hold in head, large enough to span every concept
IT design load2.5 MW critical (2.632 MVA at PF 0.95)"Critical load" = sum of UPS-fed IT power
Total facility design load (peak)~ 5.0 MW peak / ~ 4.5 MW continuous demandIT 2.5 MW + mech ~ 1.8 MW + BOP 0.2 MW
Topology2N (per Uptime Tier III equivalent)Two completely independent paths, each carries full IT load
Footprint200 ft × 300 ft × 25 ft tall~ 60,000 sq ft total
IT halls2 (Row A + Row B), 1.25 MW eachSymmetric layout, one row per side
Average rack density~ 12 kW per rack (104 racks per row)Mix of standard servers + GPU-dense nodes
Climate zoneASHRAE Zone 4A (mixed-humid, e.g., Northern Virginia)Affects mech sizing + ASHRAE 90.4 compliance
Year built2026 (current NEC = 2023; ASHRAE 90.1-2022)Sets code basis

Electrical — Sources & Distribution

EquipmentSpecPer Side
Utility service12.47 kV, 3φ, 60 Hz, primary metered, two independent feedersOne feeder per side (true 2N at utility level)
Available fault current at PCC50 kA RMS symmetric at 12.47 kV (X/R ≈ 8.5)
Service transformers2 × 2,500 kVA pad-mount, 12.47 kV–480Y/277V, %Z = 5.75, Δ-Y grounded1 per side · TX-A and TX-B
Standby generators2 × 2,500 kW (3,125 kVA at 0.8 PF) Tier 4 final diesel1 per side · GEN-A and GEN-B
ATS2 × 4,000 A bypass-isolation, open-transition1 per side · ATS-A and ATS-B
480V switchgear2 × 4,000 A buses, 65 kA AIC, GFP per NEC 230.951 per side · 480V SWGR-A and SWGR-B (cross-tie normally open)
UPS4 × 1,250 kVA online double-conversion, 5-min ride-through2 per side · UPS-A1 + UPS-A2; UPS-B1 + UPS-B2
UPS batteryVRLA 540V strings (270 cells × 2V), 300 Ah cells, 2 strings per UPS for N+12,160 cells total facility
PDUs500 kVA, 480V → 415Y/240V, K-13 isolation transformer + integral panelMultiple per side (typical 4-6 per row)
RPPs415Y/240V, 400A bus, 42-circuit panelboardsOne per row of racks
Rack PDU strips415Y/240V or 240V split-phase, dual-fed (A + B)2 per rack (one from A, one from B path)

Electrical — Mechanical Loads (Side A; Side B is identical)

EquipmentQuantity per sideEach (HP / kW)FLA at 480VNotes
Centrifugal chillers (CH-1, CH-2 on Side A)2 + 1 standby across both sides (3 + 1 N+1)450 HP / 337 kW each480 A (per NEC 430.250)VFD-driven; CH-1 + CH-2 on Side A; CH-3 + CH-4 on Side B
Condenser water pumps275 HP / 56 kW each96 AVFD-driven, one per chiller
CRAH fans (Computer Room Air Handlers)450 HP / 37 kW each65 AVFD-driven, modulating with cooling demand
Cooling tower fans230 HP / 22 kW each40 AVFD-driven
Make-up water + glycol pumps25 HP / 4 kW each7.6 A
Mech room lighting + receps15 kVA18 A
IT hall lighting + lifesafety22 kVA27 A

Side A — Load Study (Canonical)

This is the official load study for Side A. Use these numbers when sections cite Atlas DC1 Side A.

LoadConnected (kW)Demand factorDemand (kW)NEC multSized (kW)
UPS-A1 + A2 input (1.25 MW IT × 1/ηUPS×0.96)1,3021.01,3021.25 (continuous, NEC 215.3)1,628
Chillers CH-1 + CH-2 (2 × 337 kW)6741.0 (peak)674NEC 430.24: 1.25 × largest + others758
Pumps CWP-1 + CWP-2 (2 × 56 kW)1121.01121.0 (other motors per 430.24)112
CRAH fans (4 × 37 kW)1490.95 (modulating)1421.0142
Cooling tower fans (2 × 22)440.7 (cycling)311.031
Lighting (mech + IT halls)221.0221.25 (continuous)28
Receptacles & misc150.5 (NEC 220.44 above 10 kVA)91.09
TOTAL — Side A2,3182,2922,708 kW

Apparent power: 2,708 / 0.95 PF = 2,851 kVA. Current at 480V: 3,430 A. Both sides sum to ~5,700 kVA total facility.

Sizing Reconciliation

ItemRequired (Side A)Spec'dMarginNotes
480V SWGR-A bus3,430 A4,000 A+17%Allows future load growth
TX-A capacity2,851 kVA2,500 kVA−12%Marginal. Real Atlas would step up to 3,000 kVA, OR accept overload during peak IT + mech coincidence (rare)
GEN-A capacity3,000 kVA (with motor starting margin)3,125 kVA (2500 kW × 1/0.8)+4%Tight. Real Atlas would size 3,000 kW (3,750 kVA) for comfort
UPS-A1 + A2 combined1,316 kVA at full IT2,500 kVA (2 × 1250)+90%2 × 1250 needed because each must carry full IT load alone (N+1 within Side A)

Fault Current Profile

BusAvailable fault current (sym RMS)Equipment AIC required
12.47 kV utility (PCC)50 kA50 kA MV switchgear
12.47 kV MV SWGR bus50 kA (utility-limited)50 kA
480V SWGR-A bus50.3 kA (per §12 calc — utility + TX-A combined)65 kA (next std up)
UPS-A1 input (480V, after feeder)~ 35 kA35 kA
UPS-A1 output (480V)UPS limits to ~ 3× rated = ~ 4,500 A22-35 kA (downstream OCPD)
PDU-A1 panel (480V)~ 25 kA25 kA
PDU-A1 secondary (415V)~ 18 kA (after K-13 isolation xfmr)22 kA
RPP-A1-1 (415V)~ 12 kA14 kA
Rack PDU strip~ 5 kA10 kA (panelboard standard)

Arc Flash Profile (Illustrative)

These numbers are illustrative for handbook purposes — real values come from running IEEE 1584-2018 with site-specific inputs (electrode configuration, exact gap, working distance, box dimensions).

BusTrip path (clearing time)Incident energy @ 18"PPE Cat
12.47 kV MV SWGRUtility 51, ~ 200 ms~ 3 cal/cm²1
480V SWGR-A (with 87B bus diff)87B trip, 4 cycles (~ 67 ms)~ 6 cal/cm²2
480V SWGR-A (without 87B)Upstream 51 backup, ~ 200 ms~ 18 cal/cm²3
UPS-A1 distributionUPS output CB ~ 500 ms~ 12 cal/cm²3
PDU-A1 panel (480V)UPS output CB ~ 500 ms~ 8 cal/cm²2
PDU-A1 panel (415V)PDU primary CB ~ 200 ms~ 4 cal/cm²1-2
RPP-A1-1 (415V)PDU sub-CB ~ 100 ms~ 2 cal/cm²1
Rack PDU branchRPP branch CB ~ 50 ms~ 0.5 cal/cm²0

Cooling System

ItemSpec
IT heat load2.5 MW = 711 tons of cooling required
Installed chiller capacity4 × 750 tons = 3,000 tons (3 + 1 N+1)
Operating chillers (max)3 (one always in standby for N+1)
Chiller load factor~ 32% (711 / 2,250) — large headroom for facility cooling + humidity
Cooling architectureWater-cooled centrifugal + cooling tower + CRAH air handling
Supply air temp72°F at server inlet (per ASHRAE TC 9.9 recommended)

Standby + Emergency Systems

SystemSpec
NEC classificationNEC 702 (optional standby) — IT load is not life safety
Life safety (NEC 700)Egress lighting, fire alarm, sprinkler controls — fed from dedicated NEC 700 ATS not shown on main SLD
Generator parallelingNONE — each gen is dedicated to its side. Open-transition ATS only.
UPS ride-through5 minutes at full load (battery sized to last well past genset start)
Genset start time10 seconds to rated voltage + frequency
ATS transfer time (open-transition)~ 200 ms outage on transfer
Net IT load impactZero — UPS rides through entire 10-sec genset start + 200-ms transfer
Genset fuel24-hour sub-base tank per genset, plus on-site 96-hour bulk tank

Grounding

ItemSpec
System grounding schemeSolidly grounded throughout
Each TX as separately derived systemYes (NEC 250.30) — own MBJ + GEC at each 480V SWGR
Each PDU as separately derived systemYes (NEC 250.30) — K-13 isolation xfmr → fresh 415Y/240V grounding at PDU
Grounding electrode systemConcrete-encased electrode (CEE/Ufer) + ground ring (250 ft 4/0 bare Cu) + building steel
GEC size2/0 Cu (per NEC 250.66)
GFP at serviceNEC 230.95 — 1,200 A pickup, 0.3 sec delay, performance-tested per 230.95(C)
IT signal reference gridPer ANSI/TIA-942, separate grid bonded to building EGC at single point

Power Quality + Compliance

MetricAtlas DC1Limit / target
PUE (Power Usage Effectiveness)1.40 (typical 2N redundancy)< 1.5 (modern); < 1.3 (hyperscale)
TDD at PCC (12.47 kV)~ 4% (after 12-pulse VFD upgrade)5% per IEEE 519 (SCR ≈ 17 → 5%)
Power factor at PCC≥ 0.950.90 utility threshold (no PFC caps — server PSUs handle this)
Voltage flickerNone significant (no large DOL motors; all VFD)IEEE 1453 Pst < 1
ASHRAE 90.1 LPD compliance0.39 W/sf in IT hall, 0.43 mech, 0.59 officeAll within limits
ASHRAE 90.4 (DC energy)MLC 0.20, ELC 0.16Within climate zone limits

Lightning + Surge Protection

SystemSpec
NFPA 780 LPSClass I — 90 air terminals @ 20 ft spacing, 18 down conductors (2/0 Cu, 60 ft spacing), bonded to ground ring
SPD at MV switchgear15 kV class surge arrester, 12 kV MCOV, 10 kA discharge
SPD at 480V SWGRType 1 hardwired ahead of main, 200 kA per phase, VPR 1500V
SPD at distribution panelsType 2, 120 kA, VPR 1200V
SPD at UPS input + outputType 2, 80/40 kA, VPR 1000/800V
SPD at rack PDUType 3 integral, 10 kA, VPR 600V

Battery Room (Class I Div 2 Group B)

ItemSpec
ClassificationClass I Div 2 Group B (hydrogen evolution from VRLA charging)
Total battery cells facility-wide2,160 (4 UPS × 2 strings × 270 cells)
Rooms4 dedicated battery rooms (one per UPS), separate from UPS room
Ventilation500 cfm each room, continuous fan + H2 sensor backup
H2 alarm thresholds1% (25% LEL) — alarm; 2% — emergency vent
Equipment in roomClass I Div 2 rated lighting + monitoring; non-sparking fan
Spill containmentNot required for VRLA (sealed); would be for flooded

PV + Energy Storage

SystemSpec
PV array200 kW DC rooftop (480 modules × 420 W), 4× 50 kW string inverters with module-level rapid shutdown
PV interconnectionSupply-side connection (NEC 705.11) at 480V SWGR-A — bypasses 120% rule
ESS500 kWh / 250 kW Li-ion (LFP) for peak shaving + ride-through augmentation
ESS roomNFPA 855 compliant — sprinklers, gas detection, ventilation, max 50 kWh per cabinet, 3 ft separation

EV Charging

EquipmentQtySpec
Level 2 EVSE (staff parking)4208V 1φ, 40 A continuous, NEMA 14-50 + J1772
DC Fast Charger (fleet)1480V 3φ, 75 kW, CCS Combo + NACS
EVEMSCoordinated 75 kW peak (vs 140 kW unmanaged) — sheds L2 during DCFC session

Single-Line Diagram

The full one-line diagram appears in §02 How Design Starts. The hero summary appears on the landing page.

Where Atlas DC1 Appears

Every section in Power Atlas uses Atlas DC1 as its primary worked example. See Connection Map for cross-references.


Canonical Atlas DC1 specifications · v1.0 · 2026-05-04
If a section number disagrees with this page, this page is correct.