PART XI Practice & Documentation
§30 / 39

LOTO

NFPA 70E Article 120 · OSHA 1910.147 · 7-step sequence · group LOTO

Lockout/Tagout is the procedure for safely isolating equipment for service. NFPA 70E and OSHA 29 CFR 1910.147 govern. Authorized vs affected workers have different responsibilities. Energy isolation devices vary by source type.

Lockout/Tagout — The Standard

Lockout/Tagout is the procedure for safely isolating equipment for service. NFPA 70E and OSHA 29 CFR 1910.147 govern. The goal: make absolutely sure no energy can reach the equipment while a worker is in contact with it.

StandardScope
OSHA 29 CFR 1910.147"Control of Hazardous Energy" — the federal LOTO standard. Applies to general industry.
OSHA 29 CFR 1926.417Construction-specific lockout requirements.
NFPA 70E Article 120"Establishing an Electrically Safe Work Condition" — the electrical LOTO procedure.
ANSI Z244.1National consensus standard for control of hazardous energy.

The 7-Step LOTO Sequence (NFPA 70E 120.5)

StepActionDetail
1Identify all sourcesUse SLDs, schedules, walk-down. Multiple sources = backfeed possible.
2Notify everyone affectedOperators, adjacent workers, customer.
3Open disconnects + breakersBoth line + load side of equipment.
4Apply locks + tagsOne worker = one lock. Personal padlock + tag with name + date.
5Discharge stored energyCapacitors, springs, batteries, hydraulic accumulators, compressed air, thermal.
6Verify de-energizationTest before touch — voltmeter on a known live source first, then on equipment, then on known live source again.
7Apply temporary protective grounds (MV/HV)For voltages > 600V — induced voltage can re-energize the line.

Authorized vs Affected vs Other Workers

RoleDefinitionTraining requirement
AuthorizedWorkers who lock out + work on energy-isolated equipmentFull LOTO training. Authorized to apply + remove their own locks.
AffectedWorkers whose job uses the equipment being LOTO'dAwareness training. Cannot apply locks. Must be informed of LOTO.
OtherWorkers in the areaGeneral awareness. Recognize a locked-out condition.

Energy Source Types

EnergyHow to isolateHow to verify
ElectricalDisconnect / breaker open + lockedVoltmeter test (live-dead-live)
HydraulicBlock valves closed + locked, pressure relievedPressure gauge at zero
PneumaticAir valve closed + locked, line ventedPressure gauge at zero
MechanicalBlock in place, springs releasedVisual inspection
ThermalAllow cool down, isolate hot/cold sourcesTemperature measurement
ChemicalBlock valves on chemical linesSniff testing for vapors, line break point
Stored (capacitors, springs)Discharge to ground via resistor; relax springsVoltmeter on capacitor; visual on springs

Equipment for LOTO

ItemPurpose
PadlockPhysically holds disconnect open. Each worker has unique key — only that worker can remove their lock.
Lockout tagAttached to padlock. Shows worker name, date, reason.
Hasp / multi-lock deviceAllows multiple workers to apply locks to the same disconnect (group LOTO).
Breaker lockoutSpecific device for circuit breakers — slides between breaker handle and ON position.
Plug lockoutEncases the plug of a portable cord, prevents reconnection.
Valve lockoutDevices to lock pneumatic/hydraulic valves in closed position.
Voltage detectorUsed in step 6 verification. Cat III rated for the voltage being tested.
Temporary protective ground (TPG)For MV/HV — connects line to ground after isolation. Required for > 600V.

Group LOTO + Complex Procedures

SituationProcedure
Single worker on simple equipmentStandard 7-step. One lock per worker.
Multiple workers, one piece of equipmentGroup LOTO. Each worker applies their own lock to a hasp. Equipment cannot be re-energized until ALL workers remove their locks.
Multiple workers, multiple disconnectsGroup LOTO with key-lock box. Master lock on disconnects holds keys; each worker locks the box.
Long-duration project (multiple shifts)Shift transfer of LOTO. Strict sign-off + verification at each shift change.
Worker cannot remove their own lockNEC + OSHA exception process — supervisor verifies worker is gone, then removes after multiple confirmations.

Worked Example 1 — Atlas DC1 LOTO with 2N Topology

Example 01 · Atlas DC1 spineServicing UPS-A1 — LOTO procedure that doesn't drop IT load

Why this is interesting

UPS-A1 serves IT Row A. In a non-2N facility, LOTO of UPS-A1 = drop IT load. In Atlas DC1's 2N topology, IT Row A is also fed from UPS-B1 via redundant paths in each rack PDU.

  1. Verify 2N path operational: Before starting, verify Side B (UPS-B1) is fully operational and able to carry full Side A IT load. Coordinate with operations team.
  2. Identify all sources of UPS-A1: Input from 480V SWGR-A. Output to PDU-A1. Battery string. Bypass static switch. UPS controls power.
  3. Notify: Site operations, IT operations, customer, fire alarm panel monitor.
  4. Open + lock disconnects: Input CB at SWGR-A (2000 A). Output CB at PDU-A1. Battery string DC CB. Static bypass disconnect.
  5. Discharge stored energy: Wait minimum 5 minutes for DC bus capacitors to discharge below 50V (per UPS manufacturer). Voltmeter verify.
  6. Verify de-energized: Live-dead-live test on UPS terminals.
  7. Battery string isolation: Battery DC voltage typically 540V. Even after AC removed, battery is still energized. Apply lock to DC CB.
  8. Work begins. If multiple workers, group LOTO with each applying their own lock to a multi-lock hasp.

Throughout this procedure

  • IT load remains fully powered via UPS-B1 redundant rack feeds.
  • Genset coordination: Verify GEN-A startup not commanded during LOTO (it would energize Side A through ATS-A but UPS-A1 is locked out anyway).
  • Bypass switch: If maintenance bypass switch present, operators may transition to bypass before LOTO — but for full LOTO, bypass also locked.

Worked Example 2 — Standard Industrial LOTO (Motor)

Example 02 · Alternate contextServicing 100 HP industrial pump motor — standard 7-step LOTO
  1. Identify sources: Power from MCC bucket. Control wiring from PLC. Mechanical: pump impeller. Hydraulic: process flow upstream.
  2. Notify: Operators, adjacent shift workers, control room.
  3. Open disconnects: MCC bucket disconnect (combination starter has pull-out handle). Open + lock.
  4. Apply control lockout: Lock the auto/manual selector switch in OFF position so PLC cannot send start signal.
  5. Isolate process: Close + lock isolation valves upstream + downstream. Bleed line pressure.
  6. Verify: Voltmeter (live-dead-live) on motor terminals. Pressure gauge on process line at zero.
  7. Work begins.
  8. After work: Close access panels. Remove locks in reverse order. Open valves. Restore power. Test run.

Drill — Quick Self-Check

Work each problem mentally; reveal to check. Goal: reflex, not deliberation.

Drill 1 · LOTO standard

Federal LOTO standard?

Drill 2 · Authorized worker

Who can apply locks?

Drill 3 · Live-dead-live

Three steps of voltage verification?

Drill 4 · Stored energy

Capacitor bank in UPS — safe to touch immediately after disconnect?

Drill 5 · MV/HV grounding

Required additional step for ≥ 600V LOTO?

If You See THIS, Think THAT

If you see…Think / use…
"LOTO" / "Lockout/Tagout"Procedure for safe energy isolation. NFPA 70E + OSHA 1910.147.
"NFPA 70E Article 120"Electrical-specific LOTO. The electrically safe work condition procedure.
"Authorized worker"Trained on full LOTO. Can apply + remove own lock.
"Affected worker"Awareness only. Cannot apply locks but must be informed.
"Live-dead-live test"Verify voltmeter on live source first, then absent on equipment, then live again. Confirms voltmeter still works.
"Group LOTO"Multiple workers each apply own lock to a multi-lock hasp.
"Stored energy"Capacitors (UPS, VFDs), springs, batteries, hydraulic accumulators. Must discharge before work.
"Temporary protective ground" (TPG)For MV/HV — bonds line to ground after isolation. Mandatory above 600V.
"Voltmeter Cat III rated"Test instrument rated for the voltage being tested. Cat III for distribution; Cat IV for service entrance.
"Single point of control" / dual disconnectTwo independent isolation methods for higher-risk work. Used for life-critical systems.
"Energized work permit"NFPA 70E 130.2 — required if working on energized equipment is justified (rare). Documented hazard analysis + PPE.