PART XI Practice & Documentation
§38 / 32

Specifications & Construction Admin

Division 26 · 3-part spec · RFIs · submittals · change orders · CA

Once design is done, the engineer transitions to advisor. Division 26 specifications govern HOW work is installed. Construction Administration runs from RFI #1 to substantial completion. Get the process right and the project ships clean.

Specifications — Division 26

Drawings show WHAT to install. Specifications show HOW. CSI MasterFormat Division 26 is the standard organization for electrical specs.

The Three-Part Format

Every Division 26 spec section follows this structure:

PartTitleWhat goes here
Part 1GeneralReferences, definitions, submittals, quality assurance, warranty, delivery + storage
Part 2ProductsApproved manufacturers, materials, equipment specifications, technical performance requirements
Part 3ExecutionInstallation, testing, commissioning, training, demonstration, cleaning, protection

Atlas DC1 Division 26 Sections (typical)

A 250-page Division 26 spec for Atlas DC1 might include:

SectionSubjectApprox pages
26 05 00Common Work Results for Electrical (general; applies to all sections)15-20
26 05 19Low-Voltage Conductors + Cables10-15
26 05 26Grounding + Bonding8-12
26 05 33Raceways + Boxes10-15
26 05 39Lighting Control Devices5-8
26 05 53Identification (labels, signs)3-5
26 09 23Lighting Control Devices8-12
26 12 13Medium-Voltage Switchgear20-30
26 22 13Medium-Voltage Transformers (pad-mount)10-15
26 24 13Switchboards (LV)10-15
26 24 16Panelboards5-8
26 24 19Motor Control Centers10-15
26 27 26Wiring Devices (receptacles, switches)5-8
26 32 13Engine Generators15-20
26 33 53Static UPS15-20
26 36 00Transfer Switches8-12
26 41 13Lightning Protection (NFPA 780)5-8
26 43 13Surge Protective Devices5-8
26 51 00Interior Lighting15-20
26 56 00Exterior Lighting10-15
27 (Comm)Communications + telecom (Div 27, distinct from electrical)30-50
28 (Safety/Security)Fire alarm, security, access control (Div 28)30-50

Construction Administration (CA) — The Engineer's Role During Construction

Once construction starts, the design engineer transitions from designer to advisor. CA activities:

ActivityDescriptionTypical frequency
RFI responsesContractor asks formal questions; engineer responds within 2-7 days. Documented.20-100/month
Submittal reviewContractor submits product cut sheets + shop drawings; engineer reviews + stamps (Approved / Approved as Noted / Rejected / Revise + Resubmit)50-500 over project
Site visitsPeriodic walkthroughs to verify installation quality + answer field questions1-4/month, more during energization
Change ordersOwner-requested or contractor-discovered changes requiring scope adjustment10-50/project
Pay application reviewEngineer reviews contractor monthly progress payment requests; approves % completionMonthly
Punch list managementEngineer walks site near substantial completion; documents deficienciesSubstantial completion + warranty walk
Witness testingEngineer attends Cx Levels 4-5 to verify performanceProject end
As-built reviewVerify contractor's record drawings reflect actual installationProject end

RFI Management — A Skill in Itself

A poorly-managed RFI process tanks projects. Best practices:

PracticeWhy
Respond within 5 business daysSlower = construction delay. Owner pays for delays.
Clear yes/no on the question, plus reasoningAvoids back-and-forth
Reference NEC article + spec section + drawingDefensible; helps contractor understand
Distinguish design intent vs additional costIf response triggers cost, document as change order trigger
CC all relevant parties (architect, structural, owner)Prevents downstream coordination issues
Use a tracking system (Bluebeam Studio, Procore, Submittal Exchange)50+ RFIs/month requires tracking; can't manage in email

Submittal Review — What Engineers Look For

ItemEngineer checks
Switchgear submittalBus rating, AIC, breaker types + ratings, dimensions vs allotted space, single-line accuracy, GFP per spec, ANSI/IEEE compliance
UPS submittalkVA rating, battery + runtime, SCCR, harmonics performance, communications interface, warranty
Generator submittalkW rating, fuel type + tank, sound attenuation, emissions tier (Tier 4 final), enclosure rating, controls + paralleling capability
Lighting fixture submittalWattage, lumens, color temp, CRI, dimming compatibility, warranty, certifications (DLC, UL)
ConductorsType (THWN-2, XHHW-2, etc.), insulation rating, manufacturer listing, voltage rating
Cable trayNEMA load class, finish, size, fittings, support spans
Coordination studyProvided by contractor's switchgear vendor — engineer verifies plot meets selectivity requirements
Arc flash studyIEEE 1584-2018 method, working distances, electrode configurations, label data

Change Orders

Construction inevitably encounters surprises. Three types:

TypeInitiated byEngineer's role
Owner changeOwner adds scope (e.g., "extend service to future addition")Design + spec the change; review contractor's cost
Field-discovered changeContractor discovers something unforeseen (e.g., conduit needs to route around buried foundation)Confirm change is necessary; verify cost
Design clarification (no cost)Engineer issues additional drawings/details to clarify intent without scope changeIssue ASI (Architect's Supplemental Instruction) or engineer's directive — typically no contractor compensation

Substantial Completion + Final Acceptance

MilestoneWhat it meansWhat follows
Substantial CompletionFacility is fit for its intended use (per architect/engineer certification). Owner can occupy.Warranty period starts. Punch list issued. Final retainage held until punch complete.
Final CompletionAll punch list items resolved. All closeout deliverables submitted.Retainage released. Final pay app approved.
Warranty WalkthroughAt ~ 11 months, engineer + owner walk facilityContractor corrects any warranty issues before warranty expires (12 months)

If You See THIS, Think THAT

If you see…Think / use…
"Division 26"Electrical specifications. CSI MasterFormat.
"Three-part spec format"Part 1 General · Part 2 Products · Part 3 Execution
"RFI" (Request for Information)Contractor's formal question. 5-day response target.
"Submittal"Contractor's product proposal. Engineer stamps approval.
"Approved as Noted"Submittal approved with engineer's notes; contractor must comply with notes
"Revise + Resubmit"Submittal not acceptable; contractor must address comments + resubmit
"ASI" (Architect's Supplemental Instruction)Clarification with no scope change — typically no cost impact
"PR" (Proposal Request)Owner asks contractor to price a potential change
"Change order"Approved scope change with contractor cost impact
"Substantial Completion"Project fit for use. Warranty starts. Punch issued.
"Punch list"List of construction defects to be corrected
"Retainage"Portion of contractor payment withheld pending final completion (typically 5-10%)
"Specs vs Drawings discrepancy"Specs typically govern (per Division 1). Always RFI when found.
"Procore" / "Submittal Exchange" / "Bluebeam Studio"RFI + submittal tracking platforms