PART XI
Practice & Documentation
§38 / 32
Specifications & Construction Admin
Division 26 · 3-part spec · RFIs · submittals · change orders · CA
Once design is done, the engineer transitions to advisor. Division 26 specifications govern HOW work is installed. Construction Administration runs from RFI #1 to substantial completion. Get the process right and the project ships clean.
Specifications — Division 26
Drawings show WHAT to install. Specifications show HOW. CSI MasterFormat Division 26 is the standard organization for electrical specs.
The Three-Part Format
Every Division 26 spec section follows this structure:
Part Title What goes here
Part 1 General References, definitions, submittals, quality assurance, warranty, delivery + storage
Part 2 Products Approved manufacturers, materials, equipment specifications, technical performance requirements
Part 3 Execution Installation, testing, commissioning, training, demonstration, cleaning, protection
Atlas DC1 Division 26 Sections (typical)
A 250-page Division 26 spec for Atlas DC1 might include:
Section Subject Approx pages
26 05 00 Common Work Results for Electrical (general; applies to all sections) 15-20
26 05 19 Low-Voltage Conductors + Cables 10-15
26 05 26 Grounding + Bonding 8-12
26 05 33 Raceways + Boxes 10-15
26 05 39 Lighting Control Devices 5-8
26 05 53 Identification (labels, signs) 3-5
26 09 23 Lighting Control Devices 8-12
26 12 13 Medium-Voltage Switchgear 20-30
26 22 13 Medium-Voltage Transformers (pad-mount) 10-15
26 24 13 Switchboards (LV) 10-15
26 24 16 Panelboards 5-8
26 24 19 Motor Control Centers 10-15
26 27 26 Wiring Devices (receptacles, switches) 5-8
26 32 13 Engine Generators 15-20
26 33 53 Static UPS 15-20
26 36 00 Transfer Switches 8-12
26 41 13 Lightning Protection (NFPA 780) 5-8
26 43 13 Surge Protective Devices 5-8
26 51 00 Interior Lighting 15-20
26 56 00 Exterior Lighting 10-15
27 (Comm) Communications + telecom (Div 27, distinct from electrical) 30-50
28 (Safety/Security) Fire alarm, security, access control (Div 28) 30-50
Construction Administration (CA) — The Engineer's Role During Construction
Once construction starts, the design engineer transitions from designer to advisor. CA activities:
Activity Description Typical frequency
RFI responses Contractor asks formal questions; engineer responds within 2-7 days. Documented. 20-100/month
Submittal review Contractor submits product cut sheets + shop drawings; engineer reviews + stamps (Approved / Approved as Noted / Rejected / Revise + Resubmit) 50-500 over project
Site visits Periodic walkthroughs to verify installation quality + answer field questions 1-4/month, more during energization
Change orders Owner-requested or contractor-discovered changes requiring scope adjustment 10-50/project
Pay application review Engineer reviews contractor monthly progress payment requests; approves % completion Monthly
Punch list management Engineer walks site near substantial completion; documents deficiencies Substantial completion + warranty walk
Witness testing Engineer attends Cx Levels 4-5 to verify performance Project end
As-built review Verify contractor's record drawings reflect actual installation Project end
RFI Management — A Skill in Itself
A poorly-managed RFI process tanks projects. Best practices:
Practice Why
Respond within 5 business days Slower = construction delay. Owner pays for delays.
Clear yes/no on the question, plus reasoning Avoids back-and-forth
Reference NEC article + spec section + drawing Defensible; helps contractor understand
Distinguish design intent vs additional cost If response triggers cost, document as change order trigger
CC all relevant parties (architect, structural, owner) Prevents downstream coordination issues
Use a tracking system (Bluebeam Studio, Procore, Submittal Exchange) 50+ RFIs/month requires tracking; can't manage in email
Submittal Review — What Engineers Look For
Item Engineer checks
Switchgear submittal Bus rating, AIC, breaker types + ratings, dimensions vs allotted space, single-line accuracy, GFP per spec, ANSI/IEEE compliance
UPS submittal kVA rating, battery + runtime, SCCR, harmonics performance, communications interface, warranty
Generator submittal kW rating, fuel type + tank, sound attenuation, emissions tier (Tier 4 final), enclosure rating, controls + paralleling capability
Lighting fixture submittal Wattage, lumens, color temp, CRI, dimming compatibility, warranty, certifications (DLC, UL)
Conductors Type (THWN-2, XHHW-2, etc.), insulation rating, manufacturer listing, voltage rating
Cable tray NEMA load class, finish, size, fittings, support spans
Coordination study Provided by contractor's switchgear vendor — engineer verifies plot meets selectivity requirements
Arc flash study IEEE 1584-2018 method, working distances, electrode configurations, label data
Change Orders
Construction inevitably encounters surprises. Three types:
Type Initiated by Engineer's role
Owner change Owner adds scope (e.g., "extend service to future addition") Design + spec the change; review contractor's cost
Field-discovered change Contractor discovers something unforeseen (e.g., conduit needs to route around buried foundation) Confirm change is necessary; verify cost
Design clarification (no cost) Engineer issues additional drawings/details to clarify intent without scope change Issue ASI (Architect's Supplemental Instruction) or engineer's directive — typically no contractor compensation
Substantial Completion + Final Acceptance
Milestone What it means What follows
Substantial Completion Facility is fit for its intended use (per architect/engineer certification). Owner can occupy. Warranty period starts. Punch list issued. Final retainage held until punch complete.
Final Completion All punch list items resolved. All closeout deliverables submitted. Retainage released. Final pay app approved.
Warranty Walkthrough At ~ 11 months, engineer + owner walk facility Contractor corrects any warranty issues before warranty expires (12 months)
If You See THIS, Think THAT
If you see… Think / use…
"Division 26" Electrical specifications. CSI MasterFormat.
"Three-part spec format" Part 1 General · Part 2 Products · Part 3 Execution
"RFI" (Request for Information) Contractor's formal question. 5-day response target.
"Submittal" Contractor's product proposal. Engineer stamps approval.
"Approved as Noted" Submittal approved with engineer's notes; contractor must comply with notes
"Revise + Resubmit" Submittal not acceptable; contractor must address comments + resubmit
"ASI" (Architect's Supplemental Instruction) Clarification with no scope change — typically no cost impact
"PR" (Proposal Request) Owner asks contractor to price a potential change
"Change order" Approved scope change with contractor cost impact
"Substantial Completion" Project fit for use. Warranty starts. Punch issued.
"Punch list" List of construction defects to be corrected
"Retainage" Portion of contractor payment withheld pending final completion (typically 5-10%)
"Specs vs Drawings discrepancy" Specs typically govern (per Division 1). Always RFI when found.
"Procore" / "Submittal Exchange" / "Bluebeam Studio" RFI + submittal tracking platforms
← §37 Previous
BESS Deep Dive
§39 Next →
All Sections