PART IX Modern Systems
§27 / 39

EV Charging

NEC 625 · L1/L2/DCFC · continuous load · EVEMS

EV charging is now standard on every commercial project. NEC 625 governs. Demand factors for EVSE differ from general receptacles. Energy Management Systems (EVEMS) reduce service-size requirements.

NEC Article 625 — EV Charging Equipment

EV charging is now standard on every commercial project. NEC 625 governs it. Demand factors differ from general receptacles. EVEMS (Energy Management Systems) reduce service-size requirements through load shedding.

Charging LevelVoltageCurrentPowerUse
Level 1120V 1φ12-16 A1.4-1.9 kWResidential, slow trickle. ~ 4-6 mi/hr added range.
Level 2208V or 240V 1φ; some 480V 3φ commercial16-80 A3.3-19.2 kWStandard residential + most commercial. ~ 10-60 mi/hr.
DC Fast Charging (DCFC)480V 3φ in; DC outvaries50-350+ kWHighway corridor, fleet refueling. ~ 100-400 mi/hr.
"Megawatt Charging" (MCS)1000V+ DC3000+ A1-3.75 MWHeavy duty trucks, buses (emerging)

EV Charging Is Always Continuous

Per NEC 625.41, EV charging is classified as a continuous load regardless of duration. So 125% multiplier applies to wire and breaker. This is true even for a 30-min DCFC session.

Branch circuit sizing
OCPD ≥ 1.25 × (EVSE rated input current)
Example: 40A EVSE → 50 A breaker minimum, with #6 Cu THWN-2.

EVEMS — Energy Management Systems (NEC 625.42)

NEC 625.42 allows demand factor reduction via Energy Management Systems (EVEMS). Without EVEMS, sum of all EVSE branches is treated as 100% continuous. With EVEMS, the system can dynamically limit total simultaneous charging power → service size much smaller.

ApproachDemand calculationService size impact
No EVEMS — full simultaneous100% × N stations × max kW each × 1.25 continuousLargest. 50 stations × 7.2 kW = 360 kW + 1.25 = 450 kW
EVEMS — dynamic load sharingConfigured maximum kW (sum < service capacity)Smallest. EVEMS limits total to e.g. 100 kW shared across all stations
EVEMS — load-shedding hierarchicalEVEMS sheds EV load when other building loads peakAllows EV charging on tight existing services

DCFC — Special Considerations

AspectDetail
Power level50, 100, 150, 175, 250, 350 kW per stall typical. 480V 3φ input.
Service requirementA 4-stall 350 kW DCFC site = 1.4 MW peak. Often requires utility upgrade.
Demand factorPer NEC 625.42(B), allowable diversity for > 1 station based on charging session statistics. Real-world: rarely all stalls full at full power.
Harmonic contentDCFC is a large rectifier — significant harmonics. Often passive or active filter required at site to meet IEEE 519.
Fault currentService often upgrades fault current at site. Equipment AIC must accommodate.
Coordination with utilityFor sites > 250 kW, often requires custom rate + demand charge structure. Utility approval lead time.

Worked Example 1 — Atlas DC1 EV Charging Station

Example 01 · Atlas DC1 spineAtlas DC1 office building parking — 4 Level 2 + 1 DCFC for fleet

Equipment list

ItemQtySpecBranch
Level 2 EVSE — staff parking4208V 1φ, 40 A continuous50 A breaker, #6 Cu in 1" EMT
DCFC — fleet vehicles1480V 3φ, 75 kW (90 A input)125 A breaker, 1/0 Cu in 1.5" EMT

Service impact analysis

  1. Without EVEMS — full simultaneous load:
    4 × (208 × 40 × 1.25) + 75 × 1.25 / 0.95 = 41.6 + 99 = 140 kW peak
  2. With EVEMS: Shed Level 2 stations during DCFC session. Max total = 75 kW DCFC OR 4 × 8.3 kW = 33 kW Level 2 = max 75 kW peak (one or other).
  3. Atlas DC1 chose EVEMS: Existing service has limited EV capacity allocation. EVEMS reduces peak from 140 to 75 kW = 50% smaller transformer needed for EV.
  4. Branch from 480V SWGR-A: Dedicated EV panel fed from 480V SWGR. 200 A branch CB, 4/0 Cu sub-feeder to EV panel.

Worked Example 2 — Highway Corridor DCFC Site

Example 02 · Alternate contextStandalone highway DCFC site — 4 stalls × 350 kW each
  1. Site demand: 4 × 350 kW = 1.4 MW peak. With 1.25 continuous = 1.75 MW.
  2. Service: Customer-owned 12.47 kV utility service with on-site step-down. 2 MVA pad-mount transformer at 480V.
  3. Switchgear: 480V switchgear with 4 × 600 A feeder breakers (one per DCFC stall).
  4. EVEMS: Often NOT used for highway DCFC because customers expect full power on demand. Service sized for full simultaneous use.
  5. Harmonics: 4 × 350 kW DCFC = significant 5th and 7th harmonic injection. Active filter required to meet IEEE 519 at PCC.
  6. Utility coordination: 12+ months lead time. Site-specific demand rate negotiation.

Drill — Quick Self-Check

Work each problem mentally; reveal to check. Goal: reflex, not deliberation.

Drill 1 · Continuous classification

EV charging is what kind of load per NEC 625.41?

Drill 2 · Level 2 voltage

Standard Level 2 EV charging voltage?

Drill 3 · DCFC voltage

DC Fast Charging input?

Drill 4 · EVEMS purpose

What does EVEMS reduce?

Drill 5 · EVSE vs EV

Where is the actual battery charger?

If You See THIS, Think THAT

If you see…Think / use…
NEC 625EV charging equipment installation rules.
"Level 1" charging120V residential. 1.4-1.9 kW. Slow.
"Level 2" charging208V or 240V. 3.3-19.2 kW. Standard residential + most commercial.
"DCFC" or "Level 3"480V 3φ in, DC out. 50-350+ kW. Highway corridor.
"EVSE"Electric Vehicle Supply Equipment. The "charger." (Actual battery charger is in the car.)
"EVEMS"Energy Management System per NEC 625.42. Limits total simultaneous EV charging power. Allows smaller services.
EV charging classified asALWAYS continuous load. 125% rule applies.
"4-stall 350 kW DCFC site"1.4 MW peak. Customer-owned MV service required typically.
NEMA 14-50 outletCommon Level 2 receptacle (50 A 240V).
"Anti-islanding for V2G"Vehicle-to-Grid bidirectional charging. Inverter standards apply.
"OCPP"Open Charge Point Protocol. Industry standard for EVSE communication.