Demand Response & Load Shedding
When the system can't carry full load (utility curtailment, generator transfer, scheduled maintenance), shed loads in priority order. ATS-based shedding works for simple cases; PMS handles complex prioritization.
Why Shed Load?
| Trigger | What's happening | Action |
|---|---|---|
| Utility outage → genset on | Genset capacity may be less than full building load | Shed non-essential to keep gen within rating |
| Genset failure during outage | Remaining gen capacity insufficient | Cascading shed to match remaining capacity |
| Utility demand response event | Utility paying customers to reduce demand during peak | Voluntary shed of pre-defined loads for incentive payment |
| Peak shaving (cost optimization) | Demand charges based on monthly peak kW | Automatic shed during forecast peaks; ESS discharge fills gap |
| Scheduled maintenance | Switchgear or transformer offline | Pre-shed loads on the affected feeder |
| Equipment overload | Local feeder approaching capacity | Shed lowest-priority load on that feeder |
Load Priority Tiers
| Tier | Description | Examples |
|---|---|---|
| 1 — Life Safety | NEC 700 — never shed | Egress lighting, fire alarm, fire pumps, smoke control |
| 2 — Critical Process | Mission-critical loads | IT (data center), surgical (hospital), refrigeration (food storage) |
| 3 — Important | Significant disruption if dropped | HVAC for occupied spaces, security systems, communication |
| 4 — Optional | Comfort, convenience | Office HVAC, parking lot lighting, EV charging, decorative lighting |
| 5 — Sheddable | First to shed; comfortable to lose | Forecast HVAC pre-cooling, EV charging during peak, water heaters |
Implementation — How Shedding Actually Works
| Method | Description | Where used |
|---|---|---|
| ATS-based shed | Auxiliary contacts on ATS open shedding contactors when on genset position | Simple emergency systems, hospitals, small DCs |
| PMS (Power Management System) | Centralized controller monitors all loads + sources, dynamically prioritizes | Large DCs, complex industrial, hyperscale |
| Smart panels / EVEMS | Panel-level controllers shed branch circuits based on programmed priority | Modern commercial, residential demand response |
| Frequency-based shed | Underfrequency relays (81U) drop loads when genset starts to slow under load | Last-resort shed when other systems fail |
| Utility load control switches | Utility-installed device that cycles AC compressor or water heater on demand | Residential utility programs (often opt-in for rate discount) |
Utility Demand Response Programs
| Program | How it works | Customer benefit |
|---|---|---|
| Time-of-Use (TOU) | Higher rates during peak hours | Shift consumption to lower-rate periods |
| Critical Peak Pricing | Even higher rates on critical days (5-15 days/yr) | Major reduction in usage during called events |
| Direct Load Control | Utility cycles HVAC or water heater during emergencies | Reduced rate; some loss of comfort |
| Demand Response (DR) | Utility pays for committed reduction during event (1-100 events/yr) | Significant payment for reliable reduction |
| Real-time pricing | Wholesale market price passed through hourly | Sophisticated customers shed when price spikes |
| Capacity programs | Customer commits to be available for grid needs (4 hr advance notice) | Annual capacity payment + per-event payment |
Worked Example 1 — Atlas DC1 Load Shed Sequence
Time sequence
| T (sec) | Event | Loads on |
|---|---|---|
| T = 0 | Utility power lost on Side A | UPS-A1, UPS-A2 ride through on battery. Mech loads off (no switchgear power). |
| T = 1 | ATS-A senses utility loss, signals GEN-A to start | Same — UPS still on battery. Cooling beginning to lose pressure. |
| T = 10 | GEN-A starts and reaches rated voltage + frequency | Same. |
| T = 12 | ATS-A closes to genset position | Side A bus re-energized from gen. UPS rectifiers come back on; battery resting. |
| T = 13 | Load priority controller checks: can GEN-A carry full Side A load? Yes (2,500 kW gen vs 2,300 kW demand). No shed needed normally. | Full load. |
| T = 13 (alternative) | If GEN-A capacity insufficient: shed CRAH fans (Tier 4) → 240 kW reduction | UPS + chillers + critical loads only. |
| T = 30 | Chiller plant restart sequence begins (CH-1 → CWP-1 → CRAH return) | Cooling restored. IT load uninterrupted throughout. |
Why this works: UPS battery ride-through (5 min) + genset (10 sec start) = 30 sec total cooling outage. IT thermal mass tolerates this without shutting down.
Worked Example 2 — Commercial Building Peak Shaving via ESS
- Demand profile: Peak 800 kW occurs 2-5 PM weekdays in summer (HVAC plus afternoon office). Off-peak: ~ 250 kW.
- Demand charge: $20/kW/mo. Annual demand cost = 800 × $20 × 12 = $192,000.
- Strategy: 500 kWh / 250 kW Li-ion ESS + automated load shed.
- Discharge profile: ESS discharges 250 kW for 2 hr during peak (3-5 PM) → reduces measured peak from 800 to 550 kW.
- Load shed (back-up): If ESS depleted, shed parking lot lighting (50 kW) + half of office HVAC (200 kW) for last 30 min of peak hour.
- Savings: Peak reduction 250 kW × $20 × 12 = $60K/yr saved. Plus ESS arbitrages day/night rates: ~$15K/yr. Total: ~$75K/yr. Payback ~ 5-7 yr.
Drill — Quick Self-Check
Work each problem mentally; reveal to check. Goal: reflex, not deliberation.
What load tier is NEVER shed?
Why is reducing peak demand valuable?
Centralized controller for complex shedding?
What ANSI device sheds load when generator slows under load?
What load class sheds first in Atlas DC1?
Demand Charges — How They Work + Math
Most commercial + industrial utility tariffs include both an ENERGY charge ($/kWh) and a DEMAND charge ($/kW). Demand is what drives peak shaving + load shedding economics.
How Demand Is Measured
| Metric | Definition |
|---|---|
| Demand interval | 15-min, 30-min, or hourly window over which average kW is computed |
| Monthly peak | Highest demand interval value during the billing month |
| Ratchet clause | Some tariffs lock the billed peak to the highest of the past 11 months — one summer peak charges all year |
| Demand charge | Monthly peak (kW) × $/kW rate |
| Time-of-Use (TOU) demand | Different $/kW rates for on-peak vs off-peak hours |
Worked Example — Peak Shaving Math
Baseline tariff
Without intervention
With 250 kW × 2-hr ESS
Plus arbitrage savings (energy)
ROI
If You See THIS, Think THAT
| If you see… | Think / use… |
|---|---|
| "Demand response" / DR program | Utility pays for load reduction during peak. 1-100 events/yr typical. |
| "Load shedding" | Dropping loads in priority order. Triggered by overload, gen capacity, or utility request. |
| "Peak shaving" | Reducing peak demand charge via ESS, shed, or generation. |
| "PMS" (Power Management System) | Centralized controller. Required for complex systems > 2 MW typically. |
| "Time-of-Use" rate | Different prices throughout the day. Drives arbitrage opportunities. |
| "Tier 1 load" | Life safety. NEVER shed. |
| "Underfrequency shedding" (81U) | Last-resort load shed when generator can't keep frequency. |
| "Direct Load Control" | Utility-installed device for residential AC/water heater. Opt-in. |
| "Critical Peak Pricing" (CPP) | Utility rate event that may happen 5-15 days/yr. Major price increase. |
| EVSE on commercial service | Often the biggest sheddable load. EVEMS implements automatic shed. |