Wind Generation
Wind is the second pillar of NCEES "alternative power generation" alongside PV. Where PV is many small DC sources combined through inverters, wind is fewer large AC machines — squirrel-cage, doubly-fed, or fully-converter-fed — feeding a medium-voltage collector substation. The PE exam asks turbine type, capacity factor, ride-through, and reactive support.
The Big Picture — From Wind to Grid
| Stage | Component | Voltage | What happens |
|---|---|---|---|
| 1. Mechanical | Rotor, gearbox (or direct drive) | — | Wind kinetic energy → shaft power |
| 2. Generator | SCIG / DFIG / PMSG | 0.69 kV typical | Shaft power → electrical power, possibly variable freq |
| 3. Pad-mount Tx | Step-up transformer at base of tower | 0.69 kV → 34.5 kV | Each turbine has its own MV step-up |
| 4. Collector | 34.5 kV underground feeders, multiple turbines per string | 34.5 kV | Up to ~ 30 turbines per circuit |
| 5. Substation | Collector → transmission step-up | 34.5 kV → 138 / 230 / 345 kV | Project-level interconnect to BPS |
| 6. POI / PCC | Point of interconnection per IEEE 1547 / NERC | Transmission | Where the wind plant meets the BES |
The Power Equation — Why You Can't Capture It All
Power available in moving air through swept area A:
Real turbines achieve Cp ≈ 0.40–0.50 in their design wind speed range. Cubic dependence on v means doubling wind speed produces 8× the power — and a turbine rated for 12 m/s wind delivers only 1/8 its rated output at 6 m/s.
Wind Turbine Generator (WTG) Types — Type 1 to Type 4
| Type | Generator | Speed range | Grid interface | Era / status |
|---|---|---|---|---|
| Type 1 | SCIG (squirrel-cage induction) | Fixed (~ 1% slip) | Direct to grid via Tx + soft starter | 1980s–early 2000s. Legacy. |
| Type 2 | WRIG (wound-rotor induction) with variable rotor resistance | ~ 10% range | Direct to grid; rotor resistance modulates speed | 1990s–early 2000s. Legacy. |
| Type 3 (DFIG) | Doubly-fed induction generator — stator direct to grid, rotor via slip-ring + back-to-back converter | ± 30% around synchronous | Stator direct; rotor through ~ 30% rated converter | ~ 60% of installed onshore wind 2010-2025. GE 1.5 / 1.7 / 2.x, Vestas V90 / V100. |
| Type 4 | Full-converter (PMSG or wound-field SG) | Full range; turbine spins at any speed | 100% of power flows through back-to-back converter | Default for new offshore + most large onshore since 2018. Siemens-Gamesa SG, Vestas V150-class, GE Haliade. |
Why Type 4 Won
Type 3 dominated 2005-2018 because the converter was small (cheap). Type 4 took over because:
| Driver | Type 3 limit | Type 4 advantage |
|---|---|---|
| Grid code compliance | FRT performance limited by partial-converter design; crowbar trips disconnect generator | Inverter inherently rides through; meets all major grid codes (FERC 661/827, NERC PRC-024) |
| Low-voltage ride-through (LVRT) | Without crowbar — converter overcurrent. With crowbar — loses dynamic Q control during the fault | Continues 4-quadrant Q support throughout the fault — improves grid stability |
| Reactive power range | ± 0.95 PF typical at full P | ± 0.85 PF or wider; even Q-only operation when P = 0 |
| Gearbox failure | 3-stage gearbox is the #1 failure mode — typical replacement cost $250 k–500 k | Direct-drive PMSG eliminates the gearbox entirely |
| Offshore | Gearbox maintenance offshore is brutally expensive | Direct-drive + sealed nacelle wins offshore |
| Grid-forming roadmap | DFIG cannot easily run grid-forming | Full-converter platform supports GFM firmware (already standard on new fleet) |
Capacity Factor — The Most-Quoted Number
Capacity factor (CF) is the ratio of actual energy produced over a period to the theoretical maximum if the turbine ran at nameplate the whole time. Wind CF is a function of site wind regime, turbine class (IEC 61400-1 Class I/II/III/IV), and availability.
IEEE 1547 + NERC — Fault Ride-Through
Wind plants must remain connected and supporting the grid during voltage and frequency disturbances of the magnitudes and durations defined by IEEE 1547-2018 (interconnection ≤ 60 kV) and NERC PRC-024-3 (BES generator performance, ≥ 100 kV). Both define an envelope: voltage vs time, frequency vs time. Inside the envelope you must stay connected; outside it you may trip.
| Disturbance | IEEE 1547-2018 Cat III | NERC PRC-024-3 |
|---|---|---|
| 0.0 pu (zero) voltage | Ride through 0.16 s (10 cycles) | Ride through 0.15 s |
| 0.5 pu voltage | Ride through 0.32 s | Per FERC Order 661 |
| 0.7 pu voltage | Ride through 2.0 s | Sustained envelope |
| 0.9 pu voltage | Continuous operation | Continuous |
| 1.2 pu voltage | Ride through 0.16 s | Ride through 0.5 s |
| 57.0 Hz (or below) | Trip after 0.16 s | Per regional reliability standard |
| 61.5 Hz (or above) | Trip after 0.16 s | Per regional |
Reactive Power Support — Voltage Control at the POI
Wind plants are required to provide reactive power within at least ± 0.95 PF at the POI under FERC Order 827 (2016). Modern Type 4 plants ship with ± 0.85 PF or wider. The interconnect study sets the actual range. Reactive support comes from three places: WTG converters themselves (most economical), STATCOM at the substation (added when WTG range alone is insufficient), and switched capacitor banks (the cheapest, but discrete steps).
Worked Example 1 — Capacity Factor for a Sample Site
- Theoretical max:100 MW × 8,760 h/yr = 876,000 MWh/yr
- Capacity factor:CF = 380,000 / 876,000 = 43.4%
- Equivalent full-load hours (FLH):FLH = CF × 8,760 = 3,802 hours/yr
- What this means physically: Plant produced its rated power equivalent for 3,802 hours; rest of the year it produced less or zero. In Texas this maps to good year-round wind, particularly nighttime and shoulder seasons.
- Compare to peers: Onshore Texas / Iowa / Kansas Class II–III sites typically 40–45% CF. Offshore N. Atlantic ≥ 50% (steadier wind). California Altamont ~ 25% (poorer wind class). Solar PV in the same Texas site would be ~ 24%.
- Revenue calculation: At $35/MWh PPA, plant revenue = 380,000 × $35 = $13.3 M/year. 100 MW × $1.5 M/MW capex ≈ $150 M project cost → simple payback ~ 11 years before tax credits, ~ 6 years with PTC.
Worked Example 2 — Sizing the Collector Substation
- Plant rating + reactive range. 100 MW at the POI, ± 0.95 PF range. Apparent power required: S = 100 / 0.95 = 105.3 MVA. Round up to 120 MVA for design margin and future flex.
- Substation transformer: 1 × 120 MVA, 34.5 / 138 kV, ONAN/ONAF/OFAF cooling, %Z = 9.5% (typical for power transformers). Δ on HV / Y-grounded on LV (or vice versa per interconnect requirement).
- Collector feeder count. Industry rule of thumb: 25–35 MW per 34.5 kV feeder, typically 5–10 turbines per feeder. For 100 MW: 4 collector feeders × 25 MW each.
- Collector feeder current at full output. I = 25,000,000 / (√3 × 34,500 × 0.95) ≈ 440 A per feeder. Use 1000 kcmil Al underground cable with ampacity ≥ 500 A (NEC 310.60(C)(83)).
- Bus configuration. 100 MW is small enough for a single-bus or sectionalized-bus arrangement (per §22). Larger plants (≥ 250 MW) typically use ring bus or breaker-and-a-half.
- Reactive support assessment. WTG reactive range from 50 turbines ≈ ± 50 MVAR. POI requirement (FERC 827, ± 0.95 PF at 100 MW) = ± 32.9 MVAR. Adequate from WTGs alone — no STATCOM needed at the substation. Add later if FRT studies show transient droops below limits.
- Protection. 87T (Tx differential), 87B (bus differential), 50/51 backup, 21 (line distance toward POI), 67 (directional), 27/59 (bus voltage), 81 (frequency). All consistent with substation protection in §22.
- Identify Type 1 / 2 / 3 / 4 WTGs from a one-line and explain the converter implications.
- Apply the wind power equation P = ½ρAv³ and compute capacity factor from annual energy.
- Distinguish IEEE 1547 ride-through requirements from NERC PRC-024 and explain when each applies.
- Size a wind plant collector substation transformer including reactive headroom for FERC 827 PF range.
- Explain why most new fleet uses full-converter direct-drive PMSG.
Drill — Quick Self-Check
Maximum theoretical Cp is ___?
In a Type 3 DFIG, what fraction of total power flows through the converter?
If wind speed doubles, available wind power increases by what factor?
Plant produced 175,000 MWh from 50 MW nameplate. CF?
Standard wind farm collector voltage in North America?
If You See THIS, Think THAT
| If you see… | Think / use… |
|---|---|
| "Type 3" or "DFIG" | Doubly-fed induction; ~ 30% partial-rated converter; legacy onshore standard. |
| "Type 4" or "PMSG" | Full-converter; default for new offshore and most new onshore. |
| "Betz limit" | Theoretical max Cp = 16/27 ≈ 0.593. |
| "Capacity factor" | Annual MWh / (MW × 8,760). Typical 30–50% wind. |
| "34.5 kV collector" | Standard MV collector network voltage in NA wind plants. |
| "FRT" / "LVRT" | Fault ride-through — must stay connected per IEEE 1547 / NERC PRC-024 envelope. |
| "FERC 661" / "FERC 827" | Wind interconnection rules: tech standards (661), reactive PF (827). |
| "Crowbar" | DFIG rotor protection — short-circuits the rotor through resistors during faults. |
| "PMSG" | Permanent-magnet synchronous gen — no field excitation, common in direct-drive Type 4. |
| "Direct drive" | No gearbox; mechanical shaft from rotor straight to generator. Standard offshore. |
| "IEC 61400-1" | Wind turbine class standard: Class I (highest wind) to Class IV (lowest wind). |
| "Pitch control" | Blade angle adjusts to limit power above rated wind speed (~ 12–13 m/s typical). |
| "Cut-in / cut-out" | Wind speeds at which the turbine starts (~ 3–4 m/s) and stops (~ 25 m/s) generating. |
| "POI" | Point of interconnection — where the wind plant meets the transmission grid. |
| "PCC" | Point of common coupling — where harmonics and voltage are measured per IEEE 519. |