Feeder Design
A feeder carries power between two pieces of distribution equipment — service to switchgear, switchgear to panel, panel to PDU. Sized like a branch circuit but with one big difference: the largest motor on the feeder gets a 25% bonus.
Branch vs Feeder vs Service — NEC Definitions
Three terms, three different sets of rules. NEC Article 100 defines them precisely.
| Conductor type | Definition (NEC 100) | NEC article | OCPD multiplier | Atlas DC1 examples |
|---|---|---|---|---|
| Branch circuit | Conductors between the final OCPD and the outlet/equipment | 210, 430 (motors) | 125% × cont (NEC 210.20). Motors: per Table 430.52 | RPP breaker → rack PDU; chiller branch CB → motor |
| Feeder | Conductors between service equipment / source and the final branch-circuit OCPD | 215, 430.24 (motor feeders) | 125% × cont (NEC 215.3). Motors: 125% largest + 100% rest (430.24) | SWGR-A → UPS-A1 input; PDU-A1 → RPP-A1-1; SWGR → MCC |
| Service conductors | Conductors from utility supply to service equipment | 230 | Calculated per Article 220 demand | Utility 12.47kV → MV switchgear primary |
| Tap conductor | Smaller conductor tapped from a larger feeder, with restrictive rules on length and termination | 240.21(B) | Special — 10ft / 25ft / 100ft tap rules | Disconnect taps in switchgear sections |
NEC 430.24 — The Motor Feeder Rule
This is the most-tested motor sizing rule in the PE exam, and one of the most-used in real practice. Whenever a feeder serves multiple motors (an MCC, a mech-room sub-panel, a chilled-water plant), the largest motor gets the 125% bonus and all others contribute their FLC at face value.
Voltage Drop on Feeders
NEC 215.2(A)(1) Informational Note recommends ≤ 3% on feeder, ≤ 5% combined feeder + branch. This is a recommendation, not a requirement, but most AHJs and engineering specs treat it as mandatory. Long feeder runs frequently dictate wire size more than ampacity does.
NEC Ch 9 Table 9 — AC resistance (75°C, copper, in steel conduit)
| Conductor | R (Ω/1000 ft) | X (Ω/1000 ft) | Effective Z @ 0.85 PF |
|---|---|---|---|
| #12 AWG | 2.0 | 0.054 | 1.74 |
| #10 AWG | 1.2 | 0.050 | 1.05 |
| #8 AWG | 0.78 | 0.052 | 0.69 |
| #6 AWG | 0.49 | 0.051 | 0.44 |
| #4 AWG | 0.31 | 0.048 | 0.29 |
| #2 AWG | 0.20 | 0.045 | 0.19 |
| 1/0 AWG | 0.12 | 0.044 | 0.13 |
| 3/0 AWG | 0.079 | 0.042 | 0.094 |
| 250 kcmil | 0.054 | 0.041 | 0.073 |
| 500 kcmil | 0.029 | 0.039 | 0.054 |
| 750 kcmil | 0.021 | 0.038 | 0.048 |
Worked Example 1 — Atlas DC1 Feeder from UPS-A1 to PDU-A1
The feeder between UPS-A1 (480V output) and PDU-A1 (480V input) — 250 ft of cable. Sized for the full UPS output rating, not just current load.
Given
Step-by-step
-
Decide the feeder ampacity basis. Must serve worst-case downstream load. Since UPS could feed multiple PDUs in real designs, size feeder to UPS full-output current (1,504 A), not just one PDU.Feeder Ibasis = 1,504 A (UPS rating). Apply 125% continuous → 1,880 A.
-
Conductor selection. 1,880 A is well above any single conductor. Need parallel runs.Try 4 parallel sets of 600 kcmil (each rated 350A at 75°C) = 4 × 350 = 1,400 A — fails.
Try 4 sets of 750 kcmil = 4 × 400 = 1,600 A — fails.
Try 5 sets of 600 kcmil = 5 × 350 = 1,750 A — fails.
Try 5 sets of 750 kcmil = 5 × 400 = 2,000 A. ✓ (Or 6 sets of 500 kcmil = 1,920 A.) -
Voltage drop check. R for 750 kcmil = 0.021 Ω/1000 ft (Table 9).VD = (√3 × 1,504 × 0.021 × 250) / 1000 / 5 (parallel paths divide R) = (1.732 × 1504 × 0.021 × 250) / 5000 = 13,684 / 5000 = 2.74 V.
%VD = 2.74 / 480 × 100 = 0.57% — excellent. Well below 3%. -
Feeder OCPD at UPS-A1 output.125% × 1,504 = 1,880 A. Round up to standard: 2,000 A molded-case CB. Or use a 1,600 A breaker if downstream coordination allows.
-
Final spec.2,000 A CB at UPS · 5 sets of 750 kcmil THWN-2 Cu in 5 separate 4" EMT/cable tray runs · 350 kcmil EGC per NEC 250.122 (Table — for 2000A breaker, EGC = 4/0 Cu)
Worked Example 2 — Apartment Building Service Feeder
The 50-unit apartment building from §03 had a calculated demand of 980 A at 208V 3φ. Now we size the actual service feeder from the utility transformer.
Given
Step-by-step
-
Service entrance breaker (or fuses) + bus. Round 980 A up to standard size: 1,200 A.
-
Conductor sizing. Need 1,200 A in parallel.3 parallel sets of 500 kcmil (each 320A) = 960 A — fails for 1,200A breaker.
4 sets of 500 kcmil = 1,280 A. ✓
Or 3 sets of 750 kcmil = 1,200 A — exactly meets. -
Neutral conductor. 3φ-4W with 120V residential loads = significant unbalanced neutral current. Often sized 100% of phase conductors for residential, even though NEC allows reduction.
-
Voltage drop check (3 sets of 750 kcmil, R = 0.021 Ω/1000 ft):VD = (√3 × 980 × 0.021 × 80) / 1000 / 3 = 2,852 / 3000 = 0.95 V. %VD = 0.95 / 208 = 0.46%. ✓
-
Final spec.1,200 A main service breaker (or 1,200 A fuse) · 3 sets of 750 kcmil Cu THWN-2 in 4" PVC underground · neutral 750 kcmil (full size) · 4/0 Cu EGC. (Or aluminum at lower cost — see §07.)
Drill — Quick Self-Check
Work each problem mentally; reveal to check. Goal: reflex, not deliberation.
A 200 A breaker feeds a sub-panel which has its own branches. The 200 A circuit is a:
350 ft of 4/0 Cu (R = 0.062 Ω/kft) carrying 180 A at 480V 3φ. %VD?
Can you tap a 400 A feeder with #6 AWG (75 A) for 8 feet without sizing the wire to 400 A?
A 4-wire feeder serves 100% nonlinear server load. Neutral sizing?
Atlas DC1 UPS-A1 = 1500 A. Continuous. Min feeder ampacity?
If You See THIS, Think THAT
| If you see… | Think / use… |
|---|---|
| "Feeder" between switchgear and panel | NEC Article 215. Sized: 125% × continuous + 100% × non-continuous, with NEC 220 demand factors applied. |
| "Multiple motors on a feeder" | NEC 430.24: 125% × largest motor FLC + 100% × all other motor FLCs + other loads. |
| "Mixed motor + non-motor on feeder" | Above formula PLUS lighting + receps with their NEC 220 demand factors. Sum. |
| Long feeder run (> 100 ft, large I) | Voltage drop check. ≤ 3% target. May need to upsize beyond ampacity-only sizing. |
| Feeder current > 400 A | Almost always parallel runs. Watch terminations and cable management. |
| "Tap conductor" (NEC 240.21) | Special rules: 10ft tap (no termination protection), 25ft tap (with restrictions), 100ft tap (industrial only). All have specific size minima. |
| "Service entrance" | NEC Article 230. Different rules from feeder — service has no upstream OCPD inside the building. Sized for full demand load. |
| "Heavy unbalanced 3φ-4W" | Neutral can carry phase current or more (with harmonics). Don't undersize neutral. |
| "Harmonic loads on the feeder" (servers, VFDs, LEDs) | Neutral becomes a current-carrying conductor for derating purposes. NEC 310.15(C). Often size neutral 200% in pure nonlinear feeders. |
| Underground feeder in PVC | NEC 310.60 different ampacity table for direct burial / duct bank. Soil thermal resistivity matters. |